Sprinklr MCIT QGCC - Malomatia
Phase 1 program status across 8 workstreams. Data as of March 27, 2026. Covers Jun 2024 – May 2026.
266
101
38%
80
action required
111
42% of total
Task distribution and workstream progress
Progress, risk level, and key dates per workstream
10 tasks · Due by 2025-08-28
7
Done
1
Active
0
Overdue
1
No Owner
22 tasks · Due by 2026-04-02
17
Done
2
Active
0
Overdue
1
No Owner
52 tasks · Due by 2026-03-31
4
Done
2
Active
17
Overdue
30
No Owner
37 tasks · Due by 2026-04-17
17
Done
4
Active
16
Overdue
31
No Owner
40 tasks · Due by 2026-04-28
7
Done
3
Active
13
Overdue
16
No Owner
27 tasks · Due by 2026-03-31
22
Done
1
Active
0
Overdue
9
No Owner
58 tasks · Due by 2025-12-24
14
Done
1
Active
34
Overdue
20
No Owner
19 tasks · Due by 2025-05-24
13
Done
1
Active
0
Overdue
3
No Owner
9 identified risks — 2 critical, 6 high
2
Require immediate action
6
Active monitoring needed
1
Track and review weekly
80 tasks are past their due dates across multiple workstreams
111 tasks (42%) have no assigned owner
Resolving UAT Issues task in AQM is overdue, blocking downstream validation and sign-off
30 Voicebot tasks have no status, indicating potential tracking gaps
30 of 52 Custom Reports tasks are unassigned
41 tasks have explicit dependencies; delays in any critical-path task cascade across workstreams
Social Care Go-Live task has no due date set despite being a critical milestone
Centralized Chatbot Go-Live is blocked by pending branding requirements from Malomatia
34 overdue tasks with 24.1% completion; majority of tasks unassigned and untracked
41 tasks with explicit blockers \u2014 critical-path bottlenecks highlighted
| Task | Workstream | Blocked By | Blocking | Assignee | Status |
|---|---|---|---|---|---|
| Agent Assist AI | Agent Assist AI | Testing and Verify English AI Accuracy | — | Isha Agarwal | In progress |
| Testing and Verify English AI Accuracy | Agent Assist AI | AI Model Training for English | UAT Support, Agent Assist Build Sign-Off | A. Elsayed | No Status |
| Model training to be started | Agent Assist AI | Confirm KB format in prod/dev environment | Validation of trained models | Isha Agarwal | No Status |
| Validation of trained models + Deployment | Agent Assist AI | Model training to be started | — | Isha Agarwal | No Status |
| UAT Support and Issue Resolution | Agent Assist AI | Testing and Verify AI Accuracy | — | Isha Agarwal | No Status |
| Agent Assist Build Sign-Off | Agent Assist AI | Testing and Verify English AI Accuracy | Agent Assist Go-Live | A. Elsayed | No Status |
| Enhancement Arabic (not in scope) | Agent Assist AI | Arabic requested info | — | Isha Agarwal | No Status |
| Agent Assist Go-Live | Agent Assist AI | Agent Assist Build Sign-Off | — | Unassigned | No Status |
20 completed tasks with actual vs. planned dates — 6 late, 3 early, 11 on time
6
Delivered Late
Worst case: +56 days (Testing & Verify AI Accuracy)
3
Delivered Early
Best case: -15 days (Internal Validation Arabic)
11
On Time
80 tasks past due date — sorted by severity
| Workstream | Task | Assignee | Due Date | Days Overdue |
|---|---|---|---|---|
| Voicebot | Malomatia to Share Call Recordings | Unassigned | 2024-06-20 | 645d |
| Voicebot | Standard TTS Model Training (EN & AR) | Unassigned | 2024-07-15 | 620d |
| Custom Reports | Voice Report (Daily/Interval) | Unassigned | 2024-08-15 | 589d |
| Custom Reports | Project Performance Report | Unassigned | 2024-08-15 | 589d |
| Custom Reports | CDR Reports (Cradle to Grave) | Unassigned | 2024-08-15 | 589d |
| Custom Reports | Agent Login Logout Report | Unassigned | 2024-08-15 | 589d |
| Custom Reports | Agent Performance Report | Unassigned | 2024-08-15 | 589d |
| Custom Reports | Agent Not Ready Report | Unassigned | 2024-08-15 | 589d |
| Custom Reports | Outbound Campaigns – Education | Unassigned | 2024-08-15 | 589d |
| Custom Reports | Outbound Campaigns – Appointment | Unassigned | 2024-08-15 | 589d |
| AQM | Standard Parameter Training | Unassigned | 2024-08-23 | 581d |
| Custom Reports | Email Report (Daily/Interval) | Zaid Qahwaji | 2024-09-05 | 568d |
Important annotations from the implementation tracker
Waiting the Product team to confirm when this will be released.
Dashboard link: space-prod16.sprinklr.com/social/insights/reporting/dashboard
Additional feasible points discussed between Malomatia and Sprinklr team to be incorporated as part of Phase 2 delivery.
Report link: space-prod16.sprinklr.com/care/insights/reporting/dashboard
Internal testing in progress.
Reporting widget enhancement to show monthly data instead of weekly data. (Standalone Phase 2 item)
Chatbot Prompt enhancements underway.
Sprinklr aims to introduce Output Guardrails for Grounding Adherence as part of roadmap by 20.7, July Release, 2025.
Task distribution across Sprinklr and Malomatia teams
Isha Agarwal
Sprinklr
Samira Charaf
Malomatia
Utkarsh Dubey
Sprinklr
Fouad Ballan
Sprinklr
A. Elsayed
Malomatia
Mayank Pathak
Sprinklr
Zaid Qahwaji
Sprinklr
Mohammed Elameer
Malomatia
Karan Wali
Sprinklr
Kamesh Sinha
Sprinklr
Vasanth Mohanraj
Sprinklr
Mohamed Arafat
Malomatia
Haritha Dharshini
Sprinklr
Govind Gaud
Sprinklr
Vedha Thangarasu
Sprinklr
Ahmed Karem
Malomatia
Nitin Verma
Sprinklr
Vanshika Gupta
Sprinklr
Priority actions for the steering committee
42% of all tasks lack accountability. Conduct an emergency resource allocation session with Sprinklr and Malomatia leads within 48 hours.
Re-baseline timelines for all overdue tasks. Categorize into: (a) still relevant, (b) descoped, (c) blocked. Escalate blockers to steering committee.
With only 24% completion and 34 overdue tasks, Hayya Chatbot needs a dedicated project manager and a 30-60-90 day recovery roadmap.
AQM has 16 overdue tasks including active UAT issues. Assign dedicated QA resource and implement daily stand-ups until sign-off.
41 tasks have explicit blockers. Agent Assist Go-Live is chained through 4 dependencies. Chatbot Go-Live blocked by Malomatia branding. Assign executive sponsors to top 5 bottleneck chains.
56% of tasks have no status. Implement mandatory weekly traffic-light reporting across all 8 workstreams to restore visibility.
Agent Assist AI and AQM show 16-56 day slippage on completed tasks. Root-cause the estimation gaps and apply buffer to remaining timelines.
Output Guardrails for Grounding Adherence expected in Sprinklr 20.7 (July 2025). Confirm timeline and plan interim mitigations for hallucination risk.